In order to keep on top of things, I wrote the following schedule to assist in working out what to do and when. This way of working was taught during my HNC and I find it very useful when breaking down tasks for a project. This will be updated when relevant.

Week 13:

Friday 23 October 2020 (Teddington)

  • Write feedback and action post from 1-1 tutorial (completed)
  • Process images from Thursday 22 October (completed)
  • Write blog post for images from Thursday 22 October (completed)

Saturday 24 October 2020 (Teddington)

  • Day off

Sunday 25 October 2020 (Teddington)

  • Bushy Park hawthorn shoot (completed)

Week 14:

Monday 26 October 2020 (Teddington)

  • Process images from 25 October 2020 (completed)
  • Write blog post for shoot (completed)

Tuesday 27 October 2020 (Teddington)

  • Continue with outstanding blog posts (images and research)
  • Prepare for Group Tutorial (complete)

Wednesday 28 October 2020 (Microsoft Teams, Teddington @10am)

  • Group Tutorial (complete)

Thursday 29 October 2020 (Teddington)

  • Walk and hawthorn recce in Bushy Park (complete)

Friday 30 October 2020 (Teddington)

  • Write blog post for feedback and actions from Group Tutorial (complete)
  • Process images from 29 October 2020 (complete)
  • Write blog post for images from 29 October 2020 (complete)
  • Continue research (complete)
  • Draft hawthorn poems and folklore post (started)
  • Study skills session with Steve @3pm – 4pm (complete)

Saturday 31 October 2020

  • Day off

Sunday 1 November 2020

  • Hawthorn recce in Bushy Park with smartphone

Week 15:

Monday 2 November 2020 (Teddington)

  • Process smartphone images taken on 1 November
  • Continue research

Tuesday 3 November 2020 (Teddington)

  • Bushy Park hawthorn shoot
  • Process images

Wednesday 4 November 2020 (Teddington)

  • Independent Practice/Study
  • Frost shoot in Bushy Park
  • Process images
  • Write relevant blog post

Thursday 5 November 2020 (Teddington)

  • Continue research

Friday 6 November 2020

  • Early morning hawthorn shoot in Bushy Park

Week 16:

Saturday 7 November 2020

  • Day off

Sunday 8 November 2020

  • Day off

Monday 9 November 2020 (Teddington)

  • Hawthorn research

Tuesday 10 November 2020 (Teddington)

  • Process images from 6 November 2020
  • Write blog post for shoot from 6 November 2020
  • Prepare images for print
  • Order prints
  • Write blog post for print images

Wednesday 11 November 2020 (Online via Microsoft Teams)

  • Gallery visits and photographer talks online

Thursday 12 November 2020

  • Write follow-up blog post/s from study trip
  • Study skills session with Steve @3pm – 4pm

Friday 13 November 2020

Week 17:

Monday 16 November 2020 (Teddington)

  • Prepare for Interim review

Tuesday 17 November 2020 (Teddington)

  • Prepare for Interim Review

Wednesday 18 November 2020 (Edward Street, Brighton @10am?)

  • Interim Review (AM) (completed)
  • Visiting Speaker (PM)

Thursday 19 November 2020 (Teddington)

  • Process verbal feedback from Interim Review (completed)
  • Write relevant blog post regarding feedback (completed)
  • Look at Black & White digital conversion (completed)
  • Look at recommended camera settings and make relevant changes (completed)
  • Write relevant blog posts (completed)

Friday 20 November 2020 (Teddington)

  • Bushy Park – revisit tree highlighted in Interim Review and take shots using new settings and different lenses (completed)
  • Process images (completed)
  • Write relevant blog post (completed)

Saturday 21 November 2020

  • Day off

Sunday 22 November 2020

  • Day off